Lebanon School District



Prior to joining forces at DAY CPM, both Mike Day and Joshua Dodson worked separately on several different Lebanon Community School District capital programs. Acting on behalf of the general contractor, Mike Day provided contract administration and financial management oversight for the district bond program. The bond program funded two new elementary schools and significant additions/remodels to eight other K-12 schools.

Previous to joining DAY CPM as a principal, Joshua Dodson worked with the Lebanon Community School District as well. Joshua provided extensive Owner Representative Services for several bond measure related projects. All of the schools built with earmarked monies from the bond were completed on schedule, within budget and in accordance to the cash flow projections of the original work plan. In fact, surplus funds at the end of the bond measure project were used for other District capital improvement projects.
Client: Lebanon SD
Location: Lebanon, OR
Project Budget: $56 Million
Completion: 2004